Introduction To Design The Installation In A Tesco Forecourt Of High-power E/v Charging Plug Bays For The Reduction Of Effects Of Climate Change
Th? objective of th? project is to strategically connect Tesco forecourts with th? ?nvironm?ntal goals of th? UK government by designing and installing high-power ?l?ctric, vehicle (EV) charging outlet bays. Th? government has set goals to reduce gr??nhous? gas emissions by 57% blow 1990 levels by 2030, achieve carbon neutrality by 2050, and phase out internal combustion engine cars by 2030. This innovative initiative aims to b?st th? targets. Tesco aims to l?v?rag? th? changing market trends and consumer behaviors by adopting new technology like as fast-charging stations and r?n?wabl? ?n?rgy. This project not only demonstrates Tesco’s dedication to sustainability, but it also makes a substantial contribution to lowering air pollution and lessening th? ?ff?cts of climate change.
Project Synopsis
Tesco’s forecourts will now have high-power EV charging outlet bays installed as part of a strategic commitment to b?st th? UK government’s ?nvironm?ntal goals. Th? initiative intends to establish Tesco as a pion??r in sustainable practices by capitalizing on th? growing use of innovative technology and r?n?wabl? ?n?rgy. Strategic communication planning, stak?hold?rs participation, and th? design and deployment of charging infrastructure ar? among th? key outputs (Adams and Blair, 2019). Stak?hold?rs encompass governmental ?ntiti?s, T?sco ?x?cutiv?s, cli?nt?l?, and technology associates. Technical specifications and regulatory compliance ar? ?xampl?s of constraints, whereas scalable and reasonably priced solutions ar? th? main emphasis of inclusions. Th? project is predicated on integrating state-of-th?-art technology and adhering to severe ?nvironm?ntal regulations, guarant??ing a favorable ?ff?ct on market share and value.
Objective of the project
Th? initiative aims to b?st th? aggressive ?nvironm?ntal standards set by th? UK government by designing and installing high-power ?l?ctric vehicle (EV) charging outlet bays in T?sco forecourts. By taking advantage of th? expanding market for ?l?ctric cars and r?n?wabl? ?n?rgy, T?sco hopes to establish itself as a pion??r in ?nvironm?ntally friendly operations and make a substantial effect in air pollution.
Analysis of cost-benefit
A significant long-term advantage is shown by th? project’s cost-benefit analysis. Even whil? th? project’s initial infrastructure and technological investment may be substantial, it complies with legal r?quir?m?nts, improves Tesco’s brand image, draws in ?co-awar? consum?rs, and ?stablish?s th? firm as a leader in th? sector (Ahmadi, 2019). Th? long-term advantages ?xc??d th? initial ?xp?ns?s and include improved market share, consumer loyalty, and grater foot traffic.
Key project deliverables
The project has some key deliverables, which can be identified through the agile framework. These are as follows,
- Report on-site assessment
- Blueprint and design of infrastructure
- Installation of EV charging bay
- Compliance documentation
- Stakeholder report6
- Implementation of performance monitoring
Key stakeholders
Internal stakeholders: Tesco BOD and management, TECO staff, stakeholders of the company
External stakeholders: UK government, Environmental agencies, suppliers, customers and general users of EV
Inclusion and exclusion of the project
Inclusion of the project: comprehensive training to Tesco staffs, continuous maintenance and monitoring of the program
Exclusion: Changes to make the existing structure of the store, expansion of the forecourt of the store
Project constraints
The project constraints are the implicit and explicit part of any project. This project is also will be facing some constraints. All the constartnista re subjective to change and adoptive nature and it will occur as the project continues. The assumptions are made but they are not far away from the actual ones. The regulatory compliance with Government standards are on of the constraints. Limitation to the budgetary nature is one of the most important and timely approval of the design of the infrastructure is one of the constraints.
Assumptions
Th? high-power EV charging ?quipm?nt that complies with legal r?quir?m?nts becoming available. Th? incorporation of a resilient performance monitoring system to monitor ?n?rgy usage trends, system health, and ?n?rgy consumption.
Justifications for the project
The justification of the project can be indicated as its synergy with th? ?nvironm?ntal goals of th? UK government supports th? project’s selection and ?stablish?s T?sco as a leader in sustainability within th? sector whil? also exhibiting corporate responsibility. An enormous market opportunity is pr?s?nt?d by th? growing demand for r?n?wabl? ?n?rgy and ?l?ctric vehicles (Amri and Latief, 2020). T?sco can gain a competitive edge, improve th? perception of its brand, and significantly lesson th? ?ff?cts of climate change by offering high-power EV charging infrastructure. Beyond being financially feasible, this project advances both social w?ll-being and Tesco’s long-term sustainability aims.
Project Time Management
M??ting deadlines set by th? government and th? market requires careful planning and tim? management. For th? project to install high-power ?l?ctric vehicle (EV) charging outlet bays in T?sco forecourts to be completed successfully and to fulfill market and government deadlines, scheduling and tim? management ar? ?ss?ntial. Tasks including infrastructure design, ?x?cution, and site inspection ar? outlined in th? Work Breakdown Structure (WBS). Th? tim? estimate and activity lists specify th? d?p?nd?nci?s and length of each task. Quick action is necessary in light of th? rapidly advancing EV technology and shifting custom?r pr?f?r?nc?s. Missed market opportunities and a decline in comp?titiv?n?ss might arise from delays (Cakmakci, 2019). Th? critical path analysis and network diagram both highlight important tasks and guarant?? their timely completion. Using ?xp?rt project software, th? Gantt chart provides a thorough p?rsp?ctiv? for ?ffici?nt project management by graphically r?pr?s?nting work sch?dul?s. Th? integration of theoretical knowledge into project scheduling and tim? management guarant??s a methodical and structured approach, hence increasing th? project’s chances of successful and timely completion. Additionally, this strategy fosters overall project r?sili?nc? by enabling flexibility in th? face of unanticipated obstacles.
Work Breakdown structure
Figure 1: WBS of the proposed project
(Source: Self-created in MS Project)
In order to facilitate ?ff?ctiv? project management, th? project’s Work Breakdown Structure (WBS) methodically divides activities into manageable compon?nts. Th? WBS moves on to a thorough site valuation and planning phase after establishing th? project scope, identifying important stak?hold?rs, and getting management approval (Gatti, 2023). Then, hiring design consultants, crating EV charging bay designs, acquiring high-power EV charging ?quipm?nt, and obtaining required licenses ar? th? different categories of infrastructure design and procurement operations. Activating th? construction crew, setting up infrastructure and charging bays, testing th? system, and securing safety certificates ar? all included in th? installation and testing phase (Hadwiansyah and Latief, 2022). A thorough and w?ll-organized approach to accomplishing project objectives is ?nsur?d by th? strategically planned installation of performance monitoring systems, stak?hold?rs communication, compliance documentation, and project closeout activities.
Time estimation and activity list
Figure 2: Time estimation and activity list of the proposed project
(Source: Self-created in MS Project)
In order to combat climate change, th? planned initiative will install high-power ?l?ctric vehicle (EV) charging outlet bays in T?sco forecourts. Th? task list and tim? estimate off?r a thorough schedule for completing th? project b?tw??n January and March 2024. Project comm?nc?m?nt, site evaluation, infrastructure design, procurement, installation, compliance paperwork, stak?hold?rs communication, performance monitoring system setup, and project closeout ar? important tasks. Important actions include hiring design ?xp?rts, securing regulatory clearances, analyzing th? forecourt site, and carrying out a thorough stak?hold?rs ?ngag?m?nt plan (Jamnuch and Vatanawood, 2019). Important activities like infrastructure design and procurement ar? balanced in th? timeframe to guarant?? timely completion and adh?r?nc? to a thr??-month window. Th? thorough diss?ction considers d?p?nd?nci?s, demonstrating a w?ll-organized strategy that supports th? project’s proper objectives (Lock, 2020). Project manag?s may ?ff?ctiv?ly monitor progress and assure th? successful development of th? EV charging infrastructure within th?-designated period by using this detailed tim? estimation and activity list.
Network diagram and critical path analysis
Figure 3: Network diagram of the project
(Source: Self-created in MS Project)
Th? project’s operations, together with their relationships and sequencing, ar? graphically r?pr?s?nt?d in th? network diagram. It displays th? critical route, or th? order of int?rd?p?nd?nt tasks that ?stablish?s th? project’s lowest feasible tim?. Important checkpoints along this ?ss?ntial journey include acquiring permissions, acquiring ?quipm?nt, installing, testing, and completing handover.
It is also possibl? to observe parallel activity streams. For instance, in th? early stages, site evaluation, infrastructure design, regulatory compliance paperwork, and communication plan creation can all be done ind?p?nd?ntly (Naufal et al., 2021). Through finish-start connections, th? int?rd?p?nd?nc? amongst these concurrent streams ar? likewise mapped. There ar? clear boundaries b?tw??n th? major phases, which include planning, comm?nc?m?nt, design, installation, monitoring system implementation, and project closeout. After overall, th? network diagram off?r a clear visual summary of th? project’s structure, making it simpler to analyze th? key route and activity d?p?nd?nci?s. It is a helpful project management tool for tracking d?v?lopm?nts and identifying any bottlenecks.
Figure 4: Critical task of the proposed project
(Source: Self-created in MS Project)
The project indicated the moist critical task through the software. The critical tasks are defining the project, and identifying key stakeholders. Management approval, impact assessment, high power EV charging technology and safety certifications, integrate staff training and monitoring the technology.
Task ID |
Task Name |
Duration |
ES |
EF |
LS |
LF |
F |
1. 1 |
Define Project Scope |
3 |
0 |
3 |
0 |
3 |
0 |
1. 2 |
Identify Key Stak?hold?rs |
2 |
3 |
5 |
3 |
5 |
0 |
1. 3 |
Obtain Management Approval |
3 |
5 |
8 |
5 |
8 |
0 |
2. 1 |
Conduct Forecourt Site Analysis |
24 |
8 |
32 |
8 |
32 |
0 |
2. 2 |
Environmental Impact Assessment |
12 |
8 |
20 |
20 |
32 |
12 |
2. 3 |
Infrastructure Design Planning |
11 |
8 |
19 |
21 |
32 |
13 |
2. 4 |
Obtain Regulatory Approvals |
6 |
32 |
38 |
32 |
38 |
0 |
3. 1 |
Engage Design Consultants |
12 |
8 |
20 |
26 |
38 |
18 |
3. 2 |
D?v?loping EV Charging Bay Blueprint |
9 |
8 |
17 |
29 |
38 |
21 |
3. 3 |
Procure High-Power EV Charging Technology |
12 |
38 |
50 |
38 |
50 |
0 |
3. 4 |
Scurf Necessary Permits |
6 |
38 |
44 |
44 |
50 |
6 |
4. 1 |
Mobilize Construction Tam |
4 |
50 |
54 |
50 |
54 |
0 |
4. 2 |
Install Charging Bays and Infrastructure |
7 |
50 |
57 |
53 |
60 |
3 |
4. 3 |
Conduct System Testing and Quality Checks |
8 |
57 |
65 |
57 |
65 |
0 |
4. 4 |
Obtain Safety Certifications |
6 |
57 |
63 |
59 |
65 |
2 |
5. 1 |
Prepare and Submit Regulatory Compliance Documents |
4 |
38 |
42 |
61 |
65 |
23 |
5. 2 |
Ensure Adh?r?nc? to Environmental Standards |
3 |
38 |
41 |
62 |
65 |
24 |
6. 1 |
D?v?loping Communication Plans |
8 |
57 |
65 |
57 |
65 |
0 |
6. 2 |
Internal Staff Training |
11 |
57 |
68 |
54 |
65 |
-3 |
6. 3 |
External Stak?hold?rs Awareness Campaign |
9 |
5 |
14 |
51 |
60 |
46 |
7. 1 |
Integrate Monitoring Technology |
5 |
65 |
70 |
65 |
70 |
0 |
7. 2 |
Conduct Training for Monitoring System Operators |
6 |
65 |
71 |
64 |
70 |
-1 |
7. 3 |
Establish Reporting Protocols |
8 |
38 |
46 |
62 |
70 |
24 |
8. 1 |
Evaluate Project Success and Lessons Learned |
5 |
70 |
75 |
70 |
75 |
0 |
8. 2 |
Handover Final Documentation |
3 |
70 |
73 |
72 |
75 |
2 |
Table 1: Critical path analysis
(Source: Self-created in MS EXCEL)
Th? above data is an example of a Critical Path Method (CPM) project schedule that lists tasks, deadlines, and d?p?nd?nci?s b?tw??n th?. Th? project’s ?ss?ntial path and possibl? flexibility ar? indicated by th? Early Start (ES), Early Finish (EF), Lath Start (LS), Lath Finish (LF), and Float (F) numbers. Tasks ?ss?ntial to completing th? project by th? deadline ar? included in th? critical route, which is ?stablish?d by zero float. Notably, th? may be a delay risk in Internal Staff Training (6. 2) due to th? negative float. Tasks including site investigation, obtaining regulatory permits, and installing infrastructure ar? all w?ll-organized by th? timeline. It ?mphasiz?s how important it is to get permissions and test th? system (Nina, 2020). It is necessary to address th? negative float in staff training in order to avoid project delays overall. K??ping an eye on these factors guarant??s ?ffici?nt project management and on-tim? completion. Th? project’s critical path is 1. 1 -> 1. 2 -> 1. 3 -> 2. 1 -> 2. 4 -> 3. 3 -> 4. 1 -> 4. 3 -> 6. 1 -> 7. 1 -> 8. 1. Th? critical route has a duration of 75 days, which is th? bare minimum n??d?d to finish th? project.
Gantt chart
Figure 5: Gantt chart of the project
(Source: Self-created in MS Project)
Th? project described in th? data that was mad available is a compr?h?nsiv? effort that ?mphasiz?s a commitment to ?nvironm?ntal sustainability and mitigating climate change by adding high-power ?l?ctric vehicle (EV) charging outlet bays. Th? plan, which starts with an 8-day project initiation phase, outlines all of th? important tasks that must be completed in order for EV infrastructure to be impl?m?nt?d successfully and on schedule. Th? delineation of scope, identification of stak?hold?rs, and approval from management ar? fundamental measures that guarant?? congruence with strategic objectives.
Important activities such performing a ?nvironm?ntal impact assessment, infrastructure design planning, and a forecourt site study ar? part of th? next 24-day site assessment and planning phase (Pasaribu et al., 2019). This step includes ?nvironm?ntal and regulatory factors in addition to logistical issues. Engaging design ?xp?rts, crating EV charging bay plans, acquiring high-power EV charging ?quipm?nt, and obtaining required licenses ar? th? main goals of th? 30-day infrastructure design and procurement phase. This ?mphasiz?s how difficult it is to crate infrastructure and how important it is to plan w?ll and follow regulations.
Figure 6: Gantt chart graph of the project
(Source: Self-created in MS Project)
During th? light-day installation and testing phase, th? construction crew is mobilized, infrastructure and charging bays ar? installed, system testing is done, and safety certificates ar? obtained. Th? significance of regulatory compliance is ?mphasiz?d by th? four days allotted to compliance paperwork, which includes crating and submitting regulatory compliance documents and making sure ?nvironm?ntal r?quir?m?nts ar? followed.
36 days ar? dedicated to stak?hold?rs communication, which includes crating communication strategies, training internal staff, and launching a ?xt?rnal awareness campaign to engage and inform key parties in a proactive manner (Portly and Portly, 2022). Th? 40-day performance monitoring system implementation phase ?mphasiz?s th? value of monitoring and evaluation in guarant??ing project success by integrating technology, conducting training, and setting up reporting procedures. Project success, and final paperwork handover ar? all part of th? five-day project closeout phase (Rush and Connolly, 2020). Th? integration of monitoring technologies and stak?hold?rs communication ar? among th? noteworthy actions on th? critical route, which highlights their crucial significance in accomplishing project goals within th? ambitious 65-day timetable. This data-driven study demonstrates a w?ll-organized project plan that takes into account several aspects, such as stak?hold?rs participation and ?nvironm?ntal impact, all of which contribute to th? main objective of mitigating th? cons?qu?nc?s of climate change
Project Finance and cost management
Effective project financing and cost management ar? ?ss?ntial for th? successful installation of high-power ?l?ctric vehicle charging plug bays. By using project finance, financial resources may be allocated and tracked ?ff?ctiv?ly, guarant??ing accountability and transparency. Tasks like cost breakdown, which includes compr?h?nsiv? ?stimat?s for site evaluation, infrastructure design, procurement, installation, and compliance, ar? carried out in this project (Soothing et al., 2019). It is used th? project finance theory as a guide to d?v?loping a thorough cost management strategy that took probable risks and contingencies into account. By using financial ideas, it was possibl? to reduce financial risks related to regulatory compliance and stak?hold?rs communication, maximize budget usage, and make sure that money was allocated to important activities. Successful cost control improves overall project management and helps th? project make money.
Figure 7: Calculation of proposed total project cost
(Source: Self-created in MS EXCEL)
Th? project is overall anticipated cost is £39, 300, which is just less than th? £40, 000 budget that is available. Th? majority of th? ?xp?ns?s ar? made up of direct charges, which total £33, 000. Th? main line items ar? labor, materials, and ?quipm?nt. Across all project phases, indirect ?xp?ns?s ar? consistently calculated at £287 each job, for a total of £2, 300, or around 5. Nine% of total ?xp?nditur?s. This takes car? of necessary overheads like utilities and office space. At 10% of th? original TPC, th? £4, 000 contingency provision off?r an r?sp?ctabl? safety not against unfor?s??n circumstances and scope modifications (Teresa et al., 2019). Th? cost breakdown presents a methodical approach whereby direct project work is adequately resourced, indirect costs ar? comfortably covered without going overboard, and contingencies and overall budget usage appear sufficient. K??ping an eye on actuals compared to this bassline as ?x?cution moves forward will enable prompt detection of any cost overruns or areas that require attention. Th? secret to reducing budget risks is to k??p enough backup plans.
Figure 8: Additional Calculation of proposed total project cost
(Source: Self-created in MS EXCEL)
Th? updated contingency figure puts th? project is overall cost at £39, 300. Th? updated contingency provision helps to explain th? slight increase in th? project budget overall, ?v?n whil? direct and indirect ?xp?ns?s stay at £33, 000 and £2, 300, respectively. Th? revised contingency provision of £4, 650, which r?pr?s?nts 10% of th? initial project cost of £40, 000, appears more acceptable for a construction project of this magnitude. When contingency is calculated as a percentage of TPC instead of th? prior flat sum of £4, 000, it is directly linked to th? complexity and scale of th? project. This will provide enough l??way for unanticipated setbacks, variance analysis adjustments, and extra safety n??ds to be aspects that might be challenging to precisely identify up front (Tinsley, 2022). A sufficient ?m?rg?ncy fund that follows th? d?v?lopm?nt of th? project is ?ss?ntial for reducing budgetary risks. Th? updated computation technique takes into account better project cost planning procedures (Venkataraman and Pinto, 2023). Project success chances appear more promising with a little more effort against uncertainty, all whil? maintaining th? intended r?sults within authorized budgetary restrictions.
Project risk and stakeholder management
Risk Management
As it assists in identifying, valuating, and mitigating possibl? risks or opportunities that might affect th? project’s objectives, risk management is ?ss?ntial to project management. Th? significance of risk management and its role in reducing and controlling hazards in th? T?sco high-power EV charging station project ar? as follows:
Identification of management of risk: Management of risk allows the management to identify potential risks in the early stages of the life cycle of the project. This early identification provides ample time to develop the strategies proved effective for mitigation of the risks and exploitation of the risks.
Enhancement of decision-making: Decision-making by project manag?s is facilitated by their comprehension of prospective hazards. This covers choices about th? project’s timeliness, money, and scope.
Enhancement of communication of stakeholders: Decision-making by project manag?s is facilitated by their comprehension of prospective hazards. This covers choices about th? project’s timeliness, money, and scope.
Allocation of resources in optimal way: Allocating resources more wisely is mad possibl? by awareness of potential dangers. Instead of being unprepared when hazards arise, resources might be allocated toward risk reduction techniques.
Project flexibility: Risks ar? a given in projects since th? ar? intrinsically unpredictable. A project’s r?sili?nc? is increased by ?ff?ctiv? risk management, which quips th? tam to overcome unfor?s??n obstacles.
Identification of environmental risks and regulatory compliance: It is probable that the risk management procedure recognized hazards related to evolving environmental laws and possible hold-ups in acquiring required authorizations. It would have been possible to create proactive strategies to deal with these issues.
Integration of technological risks: Th? project tam may have recognized issues associated with th? availability and compatibility of high-power EV charging technology given its integration. It would have b??n possibl? to prepare backup plans for any unanticipated technology difficulties.
Engagement of stakeholder risks: Stakeholder involvement risks may have been recognized, such as opposition from nearby communities or electric vehicle users (Cakmakci, 2019). A plan for communicating with stakeholders may have been created to address these issues and guarantee support.
Risks of budgetary overrun: Potential risks for of budget overruns war probably d?t?ct?d by th? cost-benefit analysis. A clear budget and backup plans would help k??p ?xp?ns?s under control and provide financial stability.
Trends in market and risks related to behavior of consumer: There may have been risks connected to changes in these trends as the project sought to take advantage of evolving consumer and industry trends. The project plan would have included techniques for ongoing monitoring and adaption.
SWOT analysis
Strengths |
Establishment of strong commitment to the sustainability goal of the UK Government. Innovation of technological innovation with EV charging stations with high power capacity. Creation of the potential high branding image and retaining loyalty of customers |
weakness |
Integration of complex technology Challenges in regulatory compliance. Constraints related to budget. |
Opportunity |
Growing market for EV and renewable sustaining energy. Competitive advantages in industry |
Threat |
Changes of rapid nature in technology. Regulatory body and local community constraints. Certainty of economic variance and investment value. |
Table 1: SWOT analysis
(Source: Self-created in MS WORD)
Completing complicated initiatives, such as th? T?sco high-power EV charging station effort, requires ?xc?ll?nt risk management. It makes proactive planning possibl?, deals with uncertainty, and strengthens th? project’s ability to bounce back from setbacks. Th? project’s strengths, w?akn?ss?s, opportunities, and threats ar? further highlighted in th? SWOT analysis, which off?r a compr?h?nsiv? understanding of its strategic position.
Figure 9: Risk register of proposed total project cost
(Source: Self-created in MS EXCEL)
This risk register, which includes risks in several areas such as ?xt?rnal, performance, compliance, etc., illustrates an organized approach to risk management. Identification is derived from a variety of sources, as ?vid?nc?d by risks such as ?quipm?nt failures, delays brought on by assessments, and variations in cost resulting from changes in supply and demand. Higher scores indicate major hazards in th? likelihood and impact matrix, which is scored on a 4x4 scale. This makes it possibl? to d?t?rmin? priority; for example, high probability/impact responses to R1 and R5 will be r?c?iv?d first. Planning includes assigning owners and actions to each risk as w?ll as appropriate tactics such as minimize, transfer, and avoid among others. Assessing risk treatments is aided by continuous monitoring of status and r?sults. For instance, moving R2 has b??n successful b?caus? th? vendor has b??n handed responsibility, but given that R4 and R5 ar? still operational, ongoing monitoring is required. Th? project would have probably had significant delays, cost overruns, and performance problems without this risk management. Instead, th? project is moving forward smoothly within tim? and resource limits thanks to early detection and mitigation efforts.
In general, th? d?v?lopm?nt of targeted mitigation plans, monitoring of risk status from a shard register, evaluation of probability and ?ff?ct, and organized identification ar? ?ss?ntial processes that show thorough project risk management (Zhang et al., 2020). This project demonstrates how risk management concepts ar? used by taking a methodical approach to risk identification, assessment, and reaction planning. Th? project team has shown initiative in handling opportunities and threats, and th? risk register functions as a single repository for recording and monitoring risks. This thorough risk management procedure strengthens th? project’s r?sili?nc? and increases th? possibility that its goals will be met.
Stakeholder management
Identification of stakeholders using power interest matrix
Figure 10: Power interest matrix
(Source: Self-created in MS EXCEL)
As th? owner and primary benefactor of th? forecourt, T?sco possesses significant authority and interest. Due to their little influence but great utilization, EV driver’s ar? very int?r?st?d in projects. Although th? show little enthusiasm, th? construction crew and design consultants have a big influence on th? project’s budget and timeline. Regulatory bodies have great control over legal compliance but little interest in it. Lastly, whil? th? have less decision-making power, th? internal project tam, which consists of th? manag?s, office, and programmers, is greatly int?r?st?d in th? project’s successful completion. For a project to be viable and ?x?cut?d, it is ?ss?ntial to manag?s ?xp?ctations and ?ngag?m?nt for these defined groups with different interests and levels of power in a ?ff?ctiv? manner.
Stakeholder communication plan
Figure 11: Stakeholder communication plan
(Source: Self-created in MS EXCEL)
Stak?hold?rs communication that is ?ff?ctiv? is ?ss?ntial to th? project’s success. For very stak?hold?rs group, th? communication strategy specifies th? goals, approaches, frequency, and owners. Involvement and alignment with T?sco, EV drivers, design consultants, th? building tam, regulatory authorities, and th? project tam ar? ?nsur?d through regular updates, communication, and customized information. This proactive strategy improves communication and facilitates th? smooth completion of th? installation project for high-power EV charging plug bays.
Personal reflection
This project improved project management abilities by highlighting how crucial it is to apply academic knowledge to practical situations. It identified areas in n??d of d?v?lopm?nt whil? displaying strengths in communication and strategic planning. Important lessons learned war th? importance of flexibility in project management and th? necessity of ongoing education. Through th? d?v?lopm?nt of leadership and communication abilities, th? ?xp?ri?nc? off?r insights into successful stak?hold?rs ?ngag?m?nt. Proactive risk management and an emphasis on adaptation will be ?ss?ntial going ahead to ensure th? success of complicated projects.
Skills, abilities or knowledge used in the project planning
In the light of my ability to use and strengthen the knowledge of the executives, the skills in my work were enhanced by completing this extensive project plan. This promoted the creation of the work breakdown structure, the schedule, and the bids for the anticipated meticulous handling of the project. I used the knowledge that I had previously acquired about the circumstances, fundamentals, and float time. Creating graphic representations such as the Gantt chart also demonstrated specific abilities. It took critical thinking and organizing in view of interest factors to oversee partners and hazards. My ability to translate academic concepts like scheduling, booking, and board extension into a real maintainability drive generally has improved. Seeking perfection through repetition is how I approach things with a growth attitude. This assignment helped me to gain my professional upgrading by regular evaluation in project management.
Key strengths and weaknesses you figured out as a project manager
As a project manager, I used my technical knowledge of electric vehicle charging infrastructure to create a comprehensive plan for installing a high-performance plug-in station. Our previous experience managing construction projects allowed us to effectively coordinate contractors and complete the installation on time and within budget. However, I underestimated the complexity of obtaining permits from local governments and utility companies.
Dealing with dense bureaucracy delayed initial site investigation and construction. In the future, we plan to involve everyone involved in the previous process to map the approval process and identify potential bottlenecks. We were able to improve communication with Tesco store management and minimize disruption to daily operations during the construction phase. As electric vehicles become more popular, optimizing the installation of charging stations on existing sites can accelerate the transition away from fossil fuels. This project provided valuable lessons for the management and implementation of sustainable infrastructure projects.
Hard, soft or leadership skills you gained because of undertaking this project
Leading this sustainability project expanded my technical knowledge of electric vehicle charging specifications, power distribution, and site design considerations - important professional skills. Improved understanding of electrical standards and permitting requirements. My soft skills also grew as I liaised with Tesco executives, contractors, utilities and local authorities. I developed communication, negotiation, and conflict resolution skills to manage competing stakeholder interests.
The importance of resilience, adaptability, and accountability was highlighted when addressing construction delays. They practiced practical leadership skills, such as making decisions under pressure when unexpected obstacles arose. Leading this complex initiative from concept to completion gained experience in communicating a compelling vision, motivating teams, and planning effective project execution strategies. The combination of technical, interpersonal, and leadership skills I have developed will help us further work to reduce the environmental impact of transportation.
The lessons learned and how would you improve in future
This project provided a valuable learning experience. Underestimating government approval led to the delay. Therefore, more comprehensive process mapping with authorities is important to identify requirements in advance. Although I have effectively addressed the technical aspects, further supervision of the contractor is required to ensure careful construction. I will conduct formal progress checks. Weekly updates can enhance communication with branch managers and increase transparency regarding construction issues (Cakmakci, 2019). Having an emergency plan in place for unforeseen events such as equipment delivery delays or material shortages can minimize the impact on your schedule.
In the future, we would also like to create information packs on charger features to educate Tesco customers about the benefits of electric cars. This project strengthened my technical knowledge and project ownership. Importantly, we have become better at coordinating stakeholders and mitigating project risks. As your sustainability efforts grow, applying these insights will streamline implementation and achieve optimal business and environmental outcomes.
Conclusion
Tesco’s forecourt installation of high-power EV charging stations is an important step toward th? UK's climate goals. By means of rigorous project, planning that includes valuations, approvals, design, procurement, installation, and monitoring, T?sco is positioned as a pion??r in sustainability and th? infrastructure facilitates th? adoption of ?l?ctric vehicles on a larger scale. Even though th? project requires sophisticated technology integration and stak?hold?rs alignment, ?x?cution r?sili?nc? is fostered by strong scheduling, risk mitigation, and communication techniques. This project allows T?sco to properly b?st an urgent n??d whil? also providing an example for other firms to follow, with both societal and competitive benefits.
References
Journals
- Adams, R.V. and Blair, E., 2019. Impact of time management behaviors on undergraduate engineering students’ performance. Sage Open, 9(1), p.2158244018824506.
- Ahmadi, A., 2019. Jurnal Time Scheduling and Cost of The Indonesian Navy Ship Development Project Using Network Diagram and Earned Value Method (Evm)(Case Study of Fast Missile Boat Development). International Journal of ASRO, 9(2), pp.87-106.
- Amri, A.U. and Latief, Y., 2020. A Work Breakdown Structure Based Material Requirement Planning Information System Using Building Information Modeling for Flat Construction Project. Journal of Computational and Theoretical Nanoscience, 17(2-3), pp.1117-1126.
- Cakmakci, M., 2019. Interaction in project management approach within industry 4.0. In Advances in Manufacturing II: Volume 1-Solutions for Industry 4.0 (pp. 176-189). Springer International Publishing.
- Gatti, S., 2023. Project finance in theory and practice: designing, structuring, and financing private and public projects. Elsevier.
- Hadwiansyah, R. and Latief, Y., 2022, March. Structural Equation Model (SEM) Correlation Between Work Breakdown Structure (WBS), Work Method and Risk Towards Cost Of Safety On Low-Cost Apartments Project. In IOP Conference Series: Materials Science and Engineering (Vol. 1232, No. 1, p. 012006). IOP Publishing.
- Jamnuch, R. and Vatanawood, W., 2019, July. Transforming activity network diagram with timed Petri nets. In 2019 12th International Conference on Information & Communication Technology and System (ICTS) (pp. 125-129). IEEE.
- Lock, D., 2020. Project management. Routledge.
- Naufal, A.M., Yufrizal, A.H., Latief, Y. and Machfudiyanto, R.A., 2021, November. Development Standard Operational Procedure of Safety Architecture Work in University of Indonesia Project Based on Work Breakdown Structure to Reduce Work Accidents. In Journal of International Conference Proceedings (Vol. 4, No. 2, pp. 254-263).
- Ninan, J., 2020. Online naturalistic inquiry in project management research: Directions for research. Project leadership and society, 1, p.100002.
- Pasaribu, B., Latief, Y. and Riantini, L.S., 2019, April. Development of Risk-Based Standardized Work Breakdown Structure (WBS) to Improve Quality Planning of Drainage Construction Work. In IOP Conference Series: Earth and Environmental Science (Vol. 258, No. 1, p. 012054). IOP Publishing.
- Portny, J.L. and Portny, S.E., 2022. Project management for dummies. John Wiley & Sons.
- Rush, D.E. and Connolly, A.J., 2020. An agile framework for teaching with scrum in the IT project management classroom. Journal of Information Systems Education.
- Sitohang, D., Latief, Y. and Riantini, L.S., 2019, April. Development of risk-based work breakdown structure (WBS) standard to improve scheduling planning of airport construction work. In IOP Conference Series: Earth and Environmental Science (Vol. 258, No. 1, p. 012052). IOP Publishing.
- Tereso, A., Ribeiro, P., Fernandes, G., Loureiro, I. and Ferreira, M., 2019. Project management practices in private organizations. Project Management Journal, 50(1), pp.6-22.
- Tinsley, R., 2022. Advanced Project Financing Structuring Risk. Euromoney Institutional Investor PLC.
- Venkataraman, R.R. and Pinto, J.K., 2023. Cost and value management in projects. John Wiley & Sons.
- Zhang, Q., Yang, S., Liao, P.C. and Chen, W., 2020. Influence mechanisms of factors on project management capability. Journal of management in engineering, 36(5), p.04020045.